November 1, 2011
On November 26, ten 6th graders will graduate from our Jungle School. They have taken the admission exam at the private Christian High School (Instituto El Rey) in Rio Viejo. All passed the exam! All the students in our Jungle School are from very poor families, and these recent graduates don't have the... See More
March 29, 2011
Good morning, the security wall is now 3/4 finished, and the foundation for the new building is about 1/2 done. There are 13-14 men working daily, and cement use is running 50 bags/day, plus lots of rebar. The electricity and water will soon be connected to the site, including our own transformer. We hop... See More
February 21, 2011
Construction work at the new orphanage building site is underway. The security wall is 1/3 finished, and >550 truckloads of gravel fill have been brought in. We need to bring water and electricity to the site at a cost of $6000 in order to continue. Please consider carrying out fundraisers to help these... See More
February 19, 2011
Good morning to all HHK supporters, Construction work at the new orphanage building site has been delayed by rains, but work is starting up again. The security wall is 1/3 finished, and >550 truckloads of gravel fill have been brought in. Excavation for the foundation of the main building is now underwa... See More
December 2, 2010
Good morning Helping Honduras Kids (HHK) is pleased to announce that the city of La Ceiba has donated a large lot for the construction of our new orphanage facility. This will be a BIG and EXPENSIVE undertaking, requiring lots of support by work teams and construction funds. We ask that you check with y... See More